CR-101 Primary Crusher — Mantle Change Isolation
Full isolation of CR-101 for mantle change. Includes upstream CV-200 feed conveyor isolation per interlock requirement.
It refers to equipment that does not exist and illustrates the elements 29 CFR 1910.147(c)(4)(ii) requires a procedure to contain. It is not a document to adopt. Under (c)(4)(i) the employer must develop and document energy control procedures specific to their own machines, and under (c)(6) must inspect them at least annually.
10 points, in sequence
CV-200 feed conveyor drive isolator. Interlocked upstream source - isolate for any CR-101 chamber work.
Feed chute gate. Blocks material ingress. STORED GRAVITATIONAL - chamber must be confirmed empty.
6.6kV main motor isolator. HIGH VOLTAGE - earthing required. Flywheel coasts up to 8 minutes.
Portable earth application point at the 6.6kV motor terminals. Applied after proving dead.
Lube system pump isolator. Isolate after the main drive has fully stopped.
Hydraulic supply isolation valve to the mantle adjustment cylinders.
Hydraulic accumulator bleed valve. STORED PRESSURE - bleed to zero and verify on the gauge.
Portable earth application point at the 11kV drive. Applied AFTER isolation and proving dead. Removed last.
Backstop holdback engagement. Prevents loaded belt runback on the incline. Must be ENGAGED.
N2 purge valve for process gas lines. Used DURING isolation to purge toxics; not isolated for the work.
What your site must supply
This example is structurally complete and factually generic. The things below are the things only you can know — and they are exactly what makes a procedure yours.
- Your own asset and isolation-point tag numbers. The tags shown are illustrative and refer to equipment that does not exist.
- The actual location of every disconnect, valve and vent on your equipment.
- Measured stored-energy magnitudes and the dwell time required to dissipate them.
- Your verification method for each point, and who is authorised to perform it.
- Any additional energy sources present on your equipment and absent here.
Author this properly, once