TK-401 Nozzle Weld Repair - Hot Work

Weld repair to the 6in outlet nozzle on TK-401. NFPA 51B hot work. Fire watch 30 minutes after work stops.

10 isolation points · Blind, Block, Disconnect, Drain, Valve, Vent
This is a worked example, not an approved procedure

It refers to equipment that does not exist and illustrates the elements 29 CFR 1910.147(c)(4)(ii) requires a procedure to contain. It is not a document to adopt. Under (c)(4)(i) the employer must develop and document energy control procedures specific to their own machines, and under (c)(6) must inspect them at least annually.

Energy isolation is not the whole job

Other standards also apply to this work

  • 29 CFR 1910.252 and NFPA 51B — hot work. Requires a hot work permit, fire watch and gas testing in addition to the isolation shown here.
  • 29 CFR 1910.146 — if the repair requires entry into the tank.
The isolation plan

10 points, in sequence

Isolate & lock Isolated, locked and tagged as part of the isolation.
Apply & verify A physical state applied and then verified — not a lockable energy isolating device.
Must stay energised Deliberately left live. Removing this supply would create a hazard rather than remove one.
10
TK-401-DRAIN Isolate & lock Drain

Tank drained, gas-freed and purged. Confirm on the gas-free certificate before any ignition source.

20
TK-401-VAPOR Isolate & lock Valve

Vapour recovery line isolation valve. Prevents hydrocarbon vapour migrating back to the work.

30
TK-401-INLET-BLIND Apply & verify Blind

Inlet line spectacle blind turned to BLANK. Positive isolation - a closed valve is not enough for hot work.

40
HW-COMBUST-35FT Apply & verify Block

Combustibles within 35 feet removed or shielded with fire blankets. Includes above, below and behind walls.

50
HW-OPENINGS Apply & verify Block

Floor and wall openings within 35 feet sealed. Sparks travel through gaps to hidden combustibles.

60
HW-EXTINGUISHER Apply & verify Block

Fire extinguisher rated 2-A:20-B:C staged within 30 feet, inspected and in date.

70
HW-CYLINDERS Apply & verify Block

Gas cylinders upright, chained and outside the hot work zone. Barrier required within 20 feet of flame.

80
HW-FIREWATCH Apply & verify Block

Fire watch posted, trained and equipped. Must REMAIN for 30 minutes after work stops - OSHA 1910.252.

90
HW-GAS-TEST Apply & verify Vent

Combustible gas test in the work zone. Any reading at or above 10 percent LEL stops the work.

100
HW-SPRINKLER Must stay energised Disconnect

Sprinkler system in service and NOT impaired. Must REMAIN LIVE - it is the fire protection for this work.

Deliberately incomplete

What your site must supply

This example is structurally complete and factually generic. The things below are the things only you can know — and they are exactly what makes a procedure yours.

  • Your own asset and isolation-point tag numbers. The tags shown are illustrative and refer to equipment that does not exist.
  • The actual location of every disconnect, valve and vent on your equipment.
  • Measured stored-energy magnitudes and the dwell time required to dissipate them.
  • Your verification method for each point, and who is authorised to perform it.
  • Any additional energy sources present on your equipment and absent here.