← Procedure library
Water & wastewater

MUD-T2 Confined Space Entry - Tank Clean and Inspect

Permit-required confined space entry into mud tank no.2 for cleaning and internal inspection. 29 CFR 1910.146.

12 isolation points · Blind, Block, Disconnect, Valve, Vent
This is a worked example, not an approved procedure

It refers to equipment that does not exist and illustrates the elements 29 CFR 1910.147(c)(4)(ii) requires a procedure to contain. It is not a document to adopt. Under (c)(4)(i) the employer must develop and document energy control procedures specific to their own machines, and under (c)(6) must inspect them at least annually.

Energy isolation is not the whole job

Other standards also apply to this work

  • 29 CFR 1910.146 — permit-required confined spaces. Entry requires its own permit, attendant and rescue provisions beyond the energy isolation shown here.
The isolation plan

12 points, in sequence

Isolate & lock Isolated, locked and tagged as part of the isolation.
Apply & verify A physical state applied and then verified — not a lockable energy isolating device.
Must stay energised Deliberately left live. Removing this supply would create a hazard rather than remove one.
10
MUD-T2-AGITATOR Isolate & lock Disconnect

Tank no.2 agitator motor disconnect at the MCC. Blades start without warning if energised.

20
MUD-T2-MUDGUN Isolate & lock Valve

Mud gun supply valve to tank no.2. High-pressure jet - can injure or knock an entrant off balance.

30
MUD-T2-SUCTION Isolate & lock Valve

Suction line valve to mud pumps 1 and 2. ENGULFMENT - tank can drain or backfill through this line.

40
MUD-T2-TRANSFER Isolate & lock Valve

Transfer line valve from the reserve pit. Second fill path - often missed.

50
MUD-T2-FILL-BLIND Apply & verify Blind

Fill line spectacle blind turned to the BLANK position. Positive isolation - a closed valve is not enough for entry.

60
MUD-T2-TRIPOD Apply & verify Block

Retrieval tripod, winch and full-body harness rigged at the top hatch. Vertical entry - retrieval line stays attached.

70
MUD-T2-VENT Must stay energised Disconnect

Forced-air ventilation blower. Must RUN CONTINUOUSLY - ventilation controls the atmosphere, it does not eliminate the hazard.

80
MUD-T2-GASMON Must stay energised Disconnect

Continuous four-gas monitor in the space. Must REMAIN LIVE - entrants evacuate on alarm.

90
MUD-T2-LIGHTING Must stay energised Disconnect

Class 1 Division 1 rated task lighting in the tank. Must REMAIN LIVE - no other light source is permitted.

100
MUD-T2-ATM-O2 Apply & verify Vent

Oxygen concentration at three levels in the tank. Acceptable 19.5 to 23.5 percent.

110
MUD-T2-ATM-LEL Apply & verify Vent

Lower explosive limit. Acceptable below 10 percent LEL.

120
MUD-T2-ATM-H2S Apply & verify Vent

Hydrogen sulphide. Acceptable below 10 ppm. Mud systems on sour wells can hold H2S in the sludge.

Deliberately incomplete

What your site must supply

This example is structurally complete and factually generic. The things below are the things only you can know — and they are exactly what makes a procedure yours.

  • Your own asset and isolation-point tag numbers. The tags shown are illustrative and refer to equipment that does not exist.
  • The actual location of every disconnect, valve and vent on your equipment.
  • Measured stored-energy magnitudes and the dwell time required to dissipate them.
  • Your verification method for each point, and who is authorised to perform it.
  • Any additional energy sources present on your equipment and absent here.